Case Study: Industrial Purchase with Build Out

Uses:
  • Building Purchase - $4,000,000
  • Renovations/Equipment - $2,750,000
  • Interest Reserve - $50,000
  • Soft Costs - $50,000
Total Project - $6,850,000


Structure:

Bank Conventional Structure:
  • Bank - 75% - $5,137,500
  • Equity - 25% - %1,712,500
Total Cash Outlay = $1,712,500



504 Structure:
  • Bank - 50% - $3,425,000
  • Growth Corp - 40% - $2,740,000
  • Equity - 10% - $685,000
Total Cash Outlay = $685,000


Total Outlay Savings Using the 504 = $1,027,500